In its October 2025 report entitled Audit of Toronto Water: Stormwater and Wastewater Contract Management, the Auditor General of Toronto called for greater oversight on delay claims involving wastewater system maintenance contracts.
The report noted that maintaining the City’s sewer systems in proper repair “is essential for providing reliable sewer services to Toronto residents and businesses, and maximizing a return on assets.” The report cautioned that a lack of infrastructure maintenance can lead to system failures and warned that in recent years “disruptive incidents in North America caused by sewer system failures have led to public health risks, harmful environmental impacts, property damage, and costly repairs.”
While the Auditor General found that most sewer repair projects were delivered on budget, the report raised concerns over the timely completion of those projects. The report noted weak record-keeping in support of change orders for project delays, stating that “requests to extend a project’s substantial performance date were not always supported by adequate documentation” and that the “lack of documentation substantiating delay events reduces accountability and hinders the ability to track who is accountable for delays.”
In fact, the report noted multiple instances in which it was “unclear whether consultants exercised sufficient scrutiny when assessing and recommending approval for time extension requests” and warned that if time extensions are approved “without sufficient justification and proper verification, the City cannot claim liquidated damages (pre-estimated compensation for losses incurred by the City) and recover financial losses due to project delays.” The audit stated that the City “must strengthen accountability and oversight of contractors and consultants to ensure timely project delivery, and confirm all contract changes are adequately supported, diligently reviewed, and approved.” It also called on the City to ensure that “consultants adequately scrutinize contract changes and progress payments before recommending approval to the City.”
The Auditor General concluded that improved change order controls “may help inform management decisions, and better plan the scope, budget and schedule for current and future projects” and that “enhanced performance evaluations and monitoring will support more effective contract management going forward.”
This report, which illustrates the importance of establishing formal protocols for contract management oversight, will be featured in the Managing Supplier Performance and Debarment module of our new Fundamentals of Canadian Government Procurement certificate program that runs in April and returns in October. Please see our current training schedule for more details.