By Paul Emanuelli

This article is an excerpt from The Art of Tendering: A Global Due Diligence Guide, which is available for purchase.

Rather than imposing predetermined specifications and contract terms in our solicitation documents and limiting ourselves to seeking the most experienced team to deliver our standardized requirements at the lowest price, negotiated Request for Proposals (RFP) enable us to seek creative solutions from the marketplace and then select the most innovative proposal, based on our evaluation criteria and process rules, for the award of a contract. However, while they enable greater flexibility in outcome, negotiated RFPs remain subject to the core due process principles that apply to all public sector tendering. This discussion surveys the following seven critical rules for maintaining procedural correctness in negotiated RFPs:

  1. Avoid Overly Prescriptive Approaches
  2. Use Transparent Rules and Criteria
  3. Keep the Award Within Scope of the RFP
  4. Keep the Selected Proponent to Its Offer
  5. Do Not Arbitrarily Terminate Negotiations
  6. Document Your Negotiations
  7. Never Start Work Before Finalizing the Deal

1. Avoid Overly Prescriptive Approaches
The first principle of negotiated RFPs is to avoid overly prescriptive approaches. Since the ultimate contract award should fall within the scope and baseline requirements contained in the original RFP, purchasing institutions should avoid boxing themselves in with overly prescriptive specifications or contract legal terms and conditions. Taking too narrow an approach in RFP scoping can impede the ability to negotiate a contract award with the proponent that submitted the best solution.

Even if a proposal could save significant time and money, the process rules would not permit the selection of that proposal if the scoping of the initial solicitation was overly prescriptive and precluded that proposed approach. For example, in its November 1984 decision in Ben Bruinsma & Sons Ltd. v. Chatham (City), the Ontario High Court of Justice granted an injunction to stop the award of a contract to an alternate proposal. The dispute involved a soccer field sodding and seeding contract. One of the bidders proposed an approach that would remove the need for one of the phases of the project, thereby reducing the overall costs and accelerating the performance time. On review, this City determined that the alternative proposal offered a better solution for meeting their needs.

However, a competing bidder challenged this process, arguing that it should have been given the opportunity to bid on the rescoped work. The Court found that the rules did not allow the City of Chatham to alter the terms of the tendered contract before making the award. It therefore granted an injunction to stop the contract award.

As this case illustrates, if the scoping of the opportunity imposes significant restrictions on innovative proposals, the purchasing institution may be precluded from evaluating and awarding a contract to that proponent. While the case in question was tendered under the strict Contract A process rules that prevent creative solutions, even a negotiated RFP would have resulted in a same dead-ended process if the original performance specifications were overly prescriptive and precluded the evaluation of competing alternative proposals based on pre-established criteria. As this case illustrates, the initial scoping decision, and the level of prescriptiveness of the specifications within the solicitation, will inform the latitude of any subsequent evaluation and award decision.

Purchasing institutions should similarly avoid the unnecessarily restrictive inclusion of legal terms and conditions for contract performance since standard term contracts are typically based on narrow assumptions that may not align with the range of possible solutions proposed by competing proponents. This can have the effect of artificially reducing the scope of competition in the proposed solution. Occupying the field with standard terms can also create friction during contract negotiation, raising issues regarding whether the “changes” required to align the contract terms with the selected proposal are within scope of the original solicitation.

The more complex a project and the more the performance details are left to competing bidders to propose in their submission, the more difficult it is in practice to include a set of standard contract terms within negotiated RFPs. A middle ground is to include terms that can serve as a starting point for contract award negotiations, but even this approach is only effective where the base assumptions of those terms more-or-less align to the selected proposal and call for relatively incidental tailoring to the contract terms. This approach does not work in situations where industry practices call for supplier-driven standard terms or where the range of potential solutions exceeds the assumptions on which the purchasing institutions standard terms are based.

For example, Integrated Project Delivery (IPD) construction contracts are based on the collaborative development of project specifications. This approach to contract performance does not lend itself to the use of traditional industry standard construction contracts. In a 2014 article in the Journal of the Canadian College of Construction Lawyers entitled “Integrated Project Delivery Agreement—A Lawyer’s Perspective”, Howard W. Ashcraft, Jr. identifies key factors for the creation of IPD agreements. These multi-party agreements are based on the joint creation of project specifications by owners, architects, and contractors working together as an integrated team. As Ashcraft explains in his article, while the IPD approach to project delivery is expanding in the United States and the United Kingdom, it remains a relatively new model in Canada. This requires Canadian lawyers to adapt to a new way of thinking about project agreements. As Ashcraft states, “IPD projects are now beginning to appear in Canada with projects underway, or completed, in Ontario, Alberta, and Saskatchewan and projects being developed or considered in other Provinces”, and that “Canadian lawyers are being asked by their clients to evaluate this new form of project delivery and advise their clients in the negotiation of IPD agreements.”

In order to enable a contract under this approach, Ashcraft notes that “the attorney must understand that IPD approaches design and construction from a fundamentally different perspective”, since successfully negotiating these agreements “requires a fresh perspective, unfettered by traditional contracting concepts”. This requires adjusting from the standard form approach to negotiating contracts, in which the standard terms serve as the focal point of the negotiation process, to negotiations that contemplate the inclusion of supplier-driven performance details and therefore call for collaborative negotiations for the development of the contract terms. As Ashcraft states, in this context, “negotiation is not about contract language”, but rather it is about “finding and defining the intersection of the parties’ interests”. In other words, the business deal comes first, then the legal terms and conditions follow. As Ashcraft warns, “in too many instances, contract language is exchanged before the key business issues are addressed, thus diverting attention away from the fundamental issues.” Furthermore, “the exchange of contract language may lock in terms that work against the parties’ needs or preferences” and the “better practice is to follow the rule: deal first, language second.”

As Ashcraft observes, since traditional standard form construction contracts are based on a fundamentally different set of assumptions regarding project roles and responsibilities, negotiating parties should avoid being anchored into those assumptions by starting their negotiations based on the standard terms from those outdated contracting models. Frustration may arise if lawyers approach the IPD negotiations with the same mindset that they would apply to traditional standard form contracts.

When using negotiated RFPs, the purchasing institution should work towards developing a term sheet of key business terms that identify the key business objectives of the project and avoid getting buried under standard boilerplate legal terms and conditions that impose specific wording based on narrow and potentially inapplicable assumptions. Project teams should take their end-objectives into consideration when developing their negotiated RFPs so that, instead of prescribing detailed standard form contract terms with contractual language that may not align with the selected proposal, a term sheet of core contractual requirements can be included in the RFP to serve as a checklist of items to be negotiated into the final contract. The details of the wording can then be finalized between the negotiating parties once the deal comes into clearer focus based on the proposal that is ultimately selected through the RFP evaluation process.

2. Use Transparent Rules and Criteria
The second principle for ensuring procedural correctness in negotiated RFPs is ensuring transparent process rules and evaluation criteria. While negotiated RFPs enable flexibility in selecting the best solution, they do not permit arbitrariness in how you apply your evaluation criteria or in how you administer your evaluation and award process.

For example, in its December 1982 decision in Aurora Pump v. Goulds Pumps, Inc., the Florida First District Court of Appeal invalidated a tendering process because the rules relating to the final price submissions were not sufficiently clear. The case dealt with an Invitation for Bids (IFB) issued by the Jacksonville Electric Authority for the manufacture and supply of power station pumps. The solicitation contemplated a two-stage, two-envelope process, wherein the contents of the technical proposals would be negotiated first with the bidders while the price envelopes remained sealed, and then bidders would be allowed to amend their initial pricing to make any required adjustments that may flow from the first-stage technical negotiations.

The Court found that instead of providing clear written instructions to the bidders, the Authority ran the competition based on unwritten procedures and failed to disclose the deadline for the submission of final revised prices. Given this failure to properly delineate the process rules, the Court determined that the Authority’s decision to reject the complainant’s final price offer was arbitrary. The Court also found that the complainant was placed at a disadvantage against competing bidders who had participated in prior procurements with the Authority and already knew the unwritten process rules regarding final price submissions. The Court therefore found that the decision to reject the complainant’s bid was invalid.

As this case illustrates, public institutions should disclose their process rules for their negotiated RFPs so that all bidders, including new bidders, are on an equal procedural footing when competing for contract awards.

Similarly, in its September 2000 determination in Re Brookfield Lepage Johnson Controls Facility Management Services, the Canadian International Trade Tribunal recognized that Article 1014 of the North American Free Trade Agreement (NAFTA) (which was since superseded by the United States-Mexico-Canada Agreement (USMCA), which also recognizes negotiated RFPs) permitted the negotiation of a contract as long as the government conducts its process with transparent process rules and evaluation criteria in compliance with applicable treaty rules. The standards established in the NAFTA negotiation protocols were based on rules for using two-staged negotiated best-and-final-offer concurrent dialogue RFPs, as recognized under the United Nations Commission on International Trade Law Model Law on Public Procurement (referred to as UN Model Procurement Law) and other treaty and statutory codes in multiple jurisdictions.

The Tribunal found that the government failed to meet those transparency standards. It criticized the lack of procedural clarity in the negotiated RFP, stating that “these provisions remain ambiguous to the point where it is difficult to determine whether, taken together, they conform to the requirements of Article 1014 of NAFTA.” For example, the Tribunal found that the government issued ambiguous clarifications to its process rules, stating that “it is not clear to the Tribunal whether certain provisions regarding negotiations were only clarified or were cancelled or superseded by the clarifications or if the provisions co-exist.” The Tribunal also noted a lack of linear precision in the process rules, stating that “it is not clear whether negotiations will be undertaken with all potential suppliers or on what basis proponents will be selected for the conduct of negotiations.”

In addition to clear process rules, the Tribunal also noted that the proper use of negotiated RFPs requires transparent evaluation criteria, stating that “the negotiation process to be used in this instance must be based, in part, on evaluation criteria, including the method for rating and evaluating the criteria clearly set out in the solicitation document.” The Tribunal determined that “the RFP is ambiguous as to the negotiation regime that will apply to this procurement” and ordered that the RFP be cancelled and reissued with more clearly developed rules and criteria.

As these cases illustrate, transparent process rules and evaluation criteria serve as the foundation for any defensible negotiated RFP process since negotiated RFPs remain subject to the same core transparency standards that apply to all public sector competitive bidding processes.

3. Keep the Award Within Scope of the RFP
The third principle of a negotiated RFP process is that the contract that is ultimately awarded should fall within the scope of the contract that was originally tendered in the RFP. The purpose of a negotiated RFP process is to identify the best supplier, based on an assessment of the skill, experience, and proposed performance methods of competing proponents. While the details of the contract requirements may not be as prescribed in the initial negotiated RFP as they would be in non-negotiated formats, the contract that emerges should fall within the scope of the originally tendered opportunity. The purpose of contract award negotiations is to finalize the contract details by integrating the selected elements of the proposal that ranked highest based on the pre-established evaluation criteria. However, the awarded contract must remain consistent with the scoping of the original opportunity since the proposals were prepared and evaluated based on that original scoping.

For example, in its March 1985 decision in Best Cleaners and Contractors Ltd. v. Canada, the Federal Court of Appeal found that the government could not award a contract that was materially different from the contract contained in the tender call. The case involved a Department of Transport tendering process for the award of an operation and maintenance contract at the Frobisher Bay Airport. The solicitation called for a two-year contract, with extension options for an additional two years that were subject to the future agreement of both parties. However, after engaging in post-bid negotiations with one of the bidders, the Department secured a four-year pricing commitment and awarded a four-year deal. A competing bidder challenged the award.

The Court of Appeal found that the Department was under a duty to award a contract that was consistent with the terms set out in the original solicitation, which called for a two-year term. As the Court of Appeal found, the parties papered the award as a two-year deal, but that documentation was a sham since the Treasury Board approvals behind the award had approved a four-year deal based on the post-bid pricing commitments negotiated between the parties. While the challenged RFP in question used a Contract A bidding process, even the use of a negotiated RFP would not likely have allowed for a material scope change in the final award since the RFP had set down a two-year original term and the other bidders were not provided an opportunity to bid on a four-year deal that doubled the scope of the award. Had the original solicitation been conducted under a negotiated RFP that requested different pricing options for two- and four-year fixed terms, with clear evaluation criteria establishing how those different options would be evaluated to identify a top-scoring proposal, then a negotiated RFP process could have permitted the award of a four-year deal. While negotiated RFPs permit the flexibility to negotiate the details of a deal, those details must be negotiated within the guardrails of the originally scoped contract opportunity and originally established process rules and evaluation criteria.

Similarly, in its March 2005 decision in Northrop Grumman Information Technology, Inc., the U.S. Government Accountability Office (GAO) found that the Treasury Department changed key contract provisions after the submission of proposals. It ordered the Department to amend and reissue its tender call, and to re-evaluate proposals based on those new submissions. The case involved a request for proposals for wide area network services linking thousands of Department locations across the US, Guam, Bermuda, the Bahamas, and Europe. The RFP called for a fixed-price contract for a three-year term with seven option years. After receiving the initial proposals, the Department faced internal pressure from within government for its decision to proceed with its own contract, rather than procuring its networking requirements under a forthcoming government-wide contract.

During contract negotiations, the Department introduced new provisions that were not part of the original RFP, including criteria that restricted the ability to exercise contract extensions, which reduced the likelihood of the contract proceeding beyond its original three-year term. As the GAO concluded, the net effect of this change was to make it less likely that the Department would exercise its extension options and more likely that it would migrate over to the government-wide contract. In effect, during the contract award negotiations, the Department de-scoped the contract from what was contemplated in the original RFP. The GAO ordered the Department to amend and reissue its RFP because the contract that it awarded varied materially from the contract that was originally put to market in the RFP.

As this case demonstrates, a contract awarded pursuant to an open tendering process should be consistent with the contract that was initially put to tender. The failure to maintain alignment between the solicitation scoping and the contract award can seriously undermine the integrity of the bidding process.

Improper post-bid scope changes can impact factors other than contract duration. For example, in the November 2015 decision in Electron Lighting Systems PVT Ltd v. Shah Investments Financials Development, the Supreme Court of India struck down the out-of-scope portion of a streetlight infrastructure contract, while preserving the remainder of that contract award. The Supreme Court determined that the advertising rights component of the awarded contract fell outside of the original tender call, stating that “the above offer relating to advertising rights was uncalled for and severable, and not a part of the work for which tender was floated.” The Supreme Court found that other bidders were not given the opportunity to bid on that part of the awarded contract. As the Supreme Court stated, “the matter regarding advertising rights was separate, and the municipal corporation which is a statutory body and instrumentality of the State should have acted fairly by making it open for all eligible to submit their offers.” The Supreme Court therefore concluded that the government “was not justified in giving the advertisement rights to the appellants without inviting tender for it” and that this part of the contract should be severed out of the award and quashed. While the in-scope part of the award could proceed, the out-of-scope advertising rights would need to be tendered.

As this case illustrates, exceeding the original scope can put that out-of-scope element, if not the entire contract award, at risk of invalidation in a legal challenge.

Similarly, in its July 2017 decision in Passenger Rail Agency of South Africa v. Swifambo Rail Agency (Pty) Ltd., the High Court of South Africa struck down a contract award after finding multiple irregularities in a tendering process that led to the purchase of 70 train locomotives. The Court found that the contract terms were improperly changed during the bidding process from a lease of the locomotives to the purchase of the locomotives. The Court concluded that the winning bidder was unfairly provided information about the purchase option and that this gave that bidder an unfair advantage over other bidders. While some bidders were apparently notified of the purchase option during a pre-bid meeting, the Court found that this information was not provided to all bidders. In fact, the Court found no evidence that the terms of the RFP were formally amended to allow for the purchase option. The Court also found material technical deviations between the tender call and the awarded contract since the winning bidder’s locomotives exceeded the maximum height requirements in the RFP. The Court stated that the terms of an awarded contract “must fall within the parameters of the specifications laid down” in the tender call. It concluded that the out-of-scope provisions rendered the contract award unlawful and struck down the entire contract.

As these cases illustrate, project teams need to be careful with how they initially scope an opportunity since their ultimate contract awards must remain within the scope of the originally tendered contract or face nullification in any resulting legal challenges.

4. Keep the Selected Proponent to Its Offer
The fourth fundamental principle of a negotiated RFP process is that the deal should only get better for the purchasing institution during contract award negotiations. While the contract award negotiations should enable the incorporation of the top-ranked proponent’s proposed performance terms, those negotiations should not allow the selected proponent to bid-and-switch by negatively changing the terms in its proposal from those contained in its final evaluated offer. Since the selected proponent’s top ranking was based on its final proposal, allowing that proponent to backslide on any element of that final ranked offer can potentially call the evaluation and proponent rankings into question. Therefore, to guard against this risk, the safe litmus test is that the deal should only get better and should never get worse for the purchasing institution.

For example, in its June 1990 determination in Re Bio-Temp Scientific Inc., the Procurement Review Board of Canada found that the government improperly granted post-bid contractual concessions that could have impacted the bidder rankings. The dispute dealt with a Department of Defence procurement for an environmental test chamber. The Board found that the Department allowed the addition of a progress payment clause to the benefit of the selected bidder during the formalization of the contract, and that this clause changed the original terms upon which proponents were evaluated and ranked. As the Board stated, “the possibility of such payments being available was not known to any of the bidders in the competition.” Given the cost of producing the test chamber, and the lengthy production and delivery schedule, the Board found that the bid prices and resulting rankings could have been altered had the progress payment option been made available to all bidders in the original solicitation. As the Board stated, had the bidders “known such a payment scheme was available, it could have affected significantly the prices bid, and of course, given the closeness of the bid prices, the order of bid standing.” In other words, the post-bid indulgences granted to the selected supplier before the contract award changed the terms of its original offer in a way that could have impacted the prior evaluation rankings and undermined the integrity of the process.

The Board also questioned whether the Department obtained value-for-money since it granted the progress payment concessions without receiving a reciprocal benefit in return. As the Board stated, “there is the question of whether the Crown got value for money for the concession it granted here” noting that the government “negotiated the progress payment clause, which is, in effect, a concession to the contractor that ought to have been reflected in a reduction in the contract price, attributable to the reduced interest costs to the contractor resulting from his ability to obtain half the cost of the work upon partial completion, rather than having to wait for payment until after delivery and installation.” In other words, the deal did not get better for the government, or, at minimum, stay equal on adjusted terms, but improved for the supplier and thereby called into question the validity of the original rankings that were based on the supplier’s original offer. As the Board stated, “the file contains no record of any attempt to obtain the required price reduction, or any reaction of the contractor other than that they accepted the inclusion of the progress payment clause into the proposed contract”.

As this case illustrates, allowing contract changes to the benefit of the selected supplier raises concerns about the integrity of the evaluation process and should therefore be avoided during contract award negotiations in a negotiated RFP process.

Similarly, in its January 2012 decision in Securitas Security Services U.S.A. Inc. v. New Jersey Department of Treasury, the Superior Court of New Jersey – Appellate Division struck down a post-bid price change in the state government’s security services contract award. The case dealt with an RFP issued by the state Department of Treasury for armed and unarmed security guard services at various state offices, which was valued at approximately $10 million per year. The contract terms contained in the RFP allowed contractors to seek annual price adjustments for wage increases that occurred “during the prior year”. However, the Department permitted the selected contractor to immediately increase the rates it had submitted in its bid, rather than seeking permission to do so on the first anniversary of the contract term as contemplated by the RFP terms. A competing bidder challenged the Department’s post-bid price adjustment. The Appellate Court ruled that the Department’s post-bid price change was in contravention of the RFP rules since the “process outlined in this RFP provision clearly envisions that the contractor must await the completion of the first year of the contract before seeking a price increase.” The Appellate Court therefore struck down the price adjustment granted by the State Department and ordered that the contractor wait a full year as required by the RFP terms prior to seeking an annual adjustment to its prices.

As this case illustrates, a court may invalidate post-bid contract changes that were outside the scope of the originally tendered contract opportunity and that gave the selected supplier an advantage over other bidders.

In conclusion, the formalization of final contract terms should align performance requirements, pricing, and legal terms into the final contract based on what was set out in the initial RFP and in the selected proposal. The deal can get better for the purchasing institution, providing that the process rules permit the negotiation of improvements, including price improvements, with the top-ranked proponent, who already won the standing as top-ranked proponent by scoring highest in the evaluation. However, the deal should never get worse for the purchasing institution. Allowing a proponent to bid-and-switch, by obtaining a top ranking with one offer and then negotiating a contract award on less attractive terms than those contained in its final scored offer, calls the integrity of the evaluation and award process into question.

This is not to say that minor negotiated adjustments to the top-ranked proposal should automatically be catastrophic to a contract award, particularly in complex projects, but any element that was changed after evaluations and during contract award negotiations should be assessed through the litmus test of the impact that the change would have had on the evaluation of the top-ranked proposal. Since any reconsideration of that final evaluation can slide the process backwards down a slippery slope, the best practice to protect the integrity of the bidding process in a negotiated RFP is for the purchasing institution to ensure that the deal only gets better, and never gets worse, during contract award negotiations.

5. Do Not Arbitrarily Terminate Negotiations
The fifth rule for negotiated RFPs is that the purchasing institution should not arbitrarily terminate contract award negotiations. Negotiated RFPs should contain clear and transparent procedural off-ramps for ending negotiations. Clearly defining the timeframe for negotiations should serve as the anchor for contract award negotiations. Negotiators should provide the selected proponent a clear final warning and final opportunity to close the deal before terminating contract award negotiations. Failing to follow those rules can compromise the defensibility of the negotiation process.

For example, in its August 1996 decision in Ottawa-Carleton Dialysis Services v. Ontario (Minister of Health), the Ontario Divisional Court ruled that the provincial Ministry of Health improperly terminated contract award negotiations with the selected proponent. The dispute dealt with an RFP for dialysis services. The Ministry selected a proponent for contract negotiations but then terminated those talks after negative articles about the proponent’s parent company, referred to below as NMC, appeared in the New York Times. The proponent brought a judicial review application, challenging the Ministry’s decision to cancel the negotiation process. The government argued that the RFP process terms reserved the right to “alter any dates in the schedule, or to cancel this RFP, at any time without any penalty or cost to the Ministry.” However, the Court ruled that the exercise of those rights remained subject to due process duties, including notice requirements.

As the Court stated, if the government “had justifiable concerns about the involvement of the American facility NMC, then these could have been addressed during negotiations”, which would have provided the supplier with “an opportunity to present their position with the possibility of terminating the association with NMC if this was a justified concern of the Ministry.” The Court found that in terminating the negotiations without warning, “the actions of the Minister of Health and the Ministry resulted in a lack of fairness to the applicants”, and that even under the RFP terms that permitted cancellation of the process, “the Minister still has a duty to act fairly.” The Court found that the Ministry failed to provide valid reasons for the cancellation of the negotiations, stating that it was unable to conclude “true reasons for the cancellation of the RFP”, and that it could “only draw the inference that it was made for political reasons or other unknown reasons outside of the provisions of the Independent Health Act.” The Court concluded that the Ministry had acted arbitrarily in cancelling the contract award negotiations and retendering its RFP. The Court allowed the government an opportunity to resume its contract award negotiations with the complainant, failing which it would strike down the new RFP.

Similarly, in its August 2006 decision in Sunoco, Inc., the Office of the New York State Comptroller ruled that the New York State Thruway Authority improperly terminated contract negotiations over the wording of a contract extension. The dispute involved an RFP for the operation of 29 fuel service facilities on the New York State Thruway. The Comptroller noted that the disagreement stemmed from the Authority’s insistence on contract language in strict accordance with the contract terms in the RFP. Sunoco sought to adjust those terms by qualifying the ability of the Authority to reject extensions only for “material” non-compliance with the performance terms. As the Comptroller noted, Sunoco raised concerns that it did not want the Authority to refuse a contract extension for trivial performance breaches, since “Sunoco’s proposal had committed the company to provide a capital investment of $30,000,000 within the first four years of the contract term, and there would be insufficient time for Sunoco to recover these costs if the contract terminated at the end of ten years.” The Authority did not agree to the proposed “materiality” change. As the Comptroller noted, “Sunoco subsequently proposed a number of alternative business terms, reflected in revised contract language offered to the Authority, in an effort to reach an agreement with the Authority on the contract renewal terms”, but none of the proposed alternatives were accepted by the Authority.

As the Comptroller summarized, in defending its termination of the negotiations, the Authority argued that it gave notice prior to its June 7, 2006 Notice of Decision to withdraw from negotiation when it established its May 4, 2006 “drop dead date for conclusion of negotiations”, something that the Authority asserted “had been communicated to Sunoco well in advance.” In support of the above-noted June 7, 2006 notice to terminate, the Authority relied on an April 14, 2006 email from its lawyer to Sunoco’s lawyer in which its lawyer emailed a revised draft of the legal agreement and wrote that in light of “the upcoming Authority Board Meeting scheduled for May 4, 2006, it would be helpful to have your comments, and those of others at Sunoco. Inc. by the middle of next week. We look forward to hearing from you.” As the Comptroller summarized, the Authority asserted that “Sunoco knew or should have known that May 4th was the key date” and that that “the Authority did not act arbitrarily or capriciously.”

The Comptroller took a different view of the matter, stating the government agency could not “terminate negotiations with the winning proposer lightly.” As the Comptroller stated:

[W]here the agency finds certain contractual terms proposed by the proposer unacceptable, it must clearly and unambiguously advise the proposer in writing: (i) that such terms are unacceptable, (ii) what terms will be acceptable, and (iii) that if the proposer is not willing to agree to the terms acceptable to the Authority by a specific date, which under the circumstances is reasonable, it will terminate negotiations and proceed to negotiate a contract with the next highest ranked proposer.

Furthermore, the Comptroller stated that “assuming that such notice is provided, it must be determined that the term or terms over which the agency breaks off negotiations must reasonably justify the award of the contract to a proposer not determined to provide best value.” In other words, the Comptroller found that the failure to come to terms should be for a reason that would justify rejecting the top-ranked proponent and proceeding to the next-best proponent, which underscored the importance of the initial rankings in providing context to the subsequent contract award negotiations. The Authority was therefore ordered back to the bargaining table for failing to provide proper notice before terminating its negotiations.

Finally, in its May 2007 ruling in Re Zenix Engineering Ltd., the Canadian International Trade Tribunal found that Defence Construction Canada (DCC) breached its process rules when it unilaterally terminated contract award negotiations with the top-ranked proponent during a negotiated RFP process. As it stated in its determination, the “Tribunal is of the view that negotiations involve a dynamic whereby parties exchange offers and counteroffers until a point where they reach either an agreement in respect of the object of the negotiations or a point where they conclude that have not reached an agreement.” The Tribunal also stated that the “concept of negotiation implies a communication between parties as to the items that are essential to reaching a compromise or an agreement. Negotiations are conducted within the limits that the parties set between themselves.”

The Tribunal found that the solicitation rules only permitted termination of negotiations when it was apparent that the parties could not conclude a deal, and that “it would only have been at that moment that DCC would have been authorized to enter into negotiations with the next ranked proponent.” The Tribunal also found that the RFP terms did not allow DCC to “unilaterally determine when the negotiations had reached the point of failure”. Rather, the Tribunal ruled that DCC should have offered the top-ranked proponent the opportunity to meet its final offer before terminating talks and proceeding to the next-ranked proponent. The Tribunal found that the government breached the fair process rules by failing to make a clear final offer before it cancelled negotiations. The Tribunal determine that this procedural irregularity was a serious breach of the procurement rules and awarded the complainant lost profits, a remedy that is recognized under Canada’s federal statutory regime. The government appealed, but in its March 2008 decision in Zenix Engineering Ltd. v. Defence Construction (1951) Ltd., Canada’s Federal Court of Appeal also found the government liable for improperly cancelling contract award negotiations without giving the top-ranked proponent the opportunity to make a final offer.

As these cases illustrate, government institutions should avoid unilaterally terminating contract award negotiations and should instead only terminate negotiations after giving the selected proponent a clear warning and final opportunity to come to terms. Failing to provide a final warning with an opportunity to make or accept a final offer can constitute an arbitrary and invalid termination of contract award negotiations in a negotiated RFP process.

6. Document Your Negotiations
The sixth rule of contract award negotiations is to clearly document your negotiations and avoid making premature commitments that could be construed as constituting a contract award. In a negotiated RFP, contract awards should be made subject to a final agreement between the parties, as evidenced by a formal signed agreement. Failing to maintain these due diligence standards can result in significant legal exposures to the purchasing institution.

For example, in its March 2007 decision in Klemke Mining Corp. v. Shell Canada Ltd., the Alberta Court of Queen’s Bench awarded $26 million in damages for the breach of a verbal agreement. The case involved a proposed mining project in the Athabasca oil sands in Alberta, Canada. The plaintiff, Klemke Mining, claimed that it entered into an oral agreement with a group of oil companies operating as a joint venture under the name Albian Sands Energy Inc. It claimed that Albian breached that agreement by failing to proceed with the agreed-upon mining project. In its defence, Albian claimed that it never entered into an agreement with Klemke Mining. The Court rejected this defence, finding that the parties had formed an enforceable contract, even if that contract was never formalized through a written agreement.

The Court determined that the parties, through a series of discussions, had established all of the terms necessary to form a contract at law. In fact, at a certain point, the parties had reduced their discussions into writing in a document they referred to as a “Memorialization.” That document, the Court found, was enough evidence to support the plaintiff’s claim that a contract had been created between the parties. The Court found that the Memorialization set out the agreed-upon terms and left no further conditions for establishing a meeting of the minds. As the Court stated, the “Memorialization is silent on any conditions left to be fulfilled”, that “legal counsel was involved in drafting” the document, and that in “preparing these documents[,] did not include standard language that the documents were subject to a formal contract or not intended to form a binding contract.” Since the were no further apparent preconditions to award, the Court ruled that the parties had struck a deal.

As the Court concluded, the failure to formalize an agreement in writing does not necessarily mean that a contract was not created at law. After determining that the parties had entered into an enforceable agreement, the Court determined that Albian breached that agreement by failing to proceed with the proposed project. The Court awarded $26 million in damages for breach of contract. While this decision was appealed, in its July 2008 ruling, the Alberta Court of Appeal dismissed the appeal and upheld the trial decision.

As this case illustrates, the failure to clearly establish pre-conditions for contract award, including the approval and signing of a formal legal agreement, exposes the purchasing institutions to future claims that its contract award negotiations resulted in the award of a contract even if that contract was never formalized.

Similarly, in its September 2013 decision in Afolau Construction v. Samoa Sports Authority, the Supreme Court of Samoa awarded extra construction costs to a contractor after the government made a series of pre- and post-award scope changes. The case dealt with a tendering process for the construction of a sports complex. The plaintiff submitted a low bid of $4.4 million, which was significantly higher than the government’s budget. The parties negotiated three rounds of scope decreases and settled on an award for a reduced project at the cost of $2.8 million. After getting Cabinet approval, the Authority reversed its prior decision and decided to award the project for the original full scope for the original amount of $4.4 million. However, given the delays, the low bidder informed the government that it could no longer do the work for its original bid price and that it now required a $370,000 increase to build to the original specifications.

The parties had conflicting accounts as to what transpired at this point, with the plaintiff claiming it received verbal assurances that its adjustments would be granted, while the government claimed it made no such commitment. To add further complexity to the dispute, the government introduced a series of additional scope changes prior to the commencement of construction. The plaintiff maintained it signed the contract for the stated sum of its original $4.4 million bid based on the government’s further assurances that it would subsequently be awarded the additional price adjustments. The plaintiff therefore sought the rectification of the contract to reflect the price increase.

As the Supreme Court summarized, when considering whether to grant a request for the rectification of a contract, courts will look at the contemporaneous written records of the parties at the time of negotiations for evidence of what they agreed to. As the Supreme Court stated, when rectification is claimed, “evidence of negotiations and all other surrounding circumstances will be received.” In doing so, the courts will place greater weight on those written records than on the unwritten recollections of the individuals who were involved in those negotiations. The Supreme Court stated that “in evaluating the best evidence, it is difficult to accept reliability of evidence that purported to be based on unaided recollection and lacked independent support from the written record.” Furthermore, the Supreme Court stated that in order to be credible, the oral evidence “of any witness of what was said at the meetings of the parties must be identified with a contemporaneous record or features of the inherent probabilities of the situation which supported the oral evidence.”

After reviewing the record, the Supreme Court found no evidence that the plaintiff had agreed to its original bid price after the expiry of the bid validity period. The Supreme Court also rejected the government’s assertion that it would have re-tendered the project, rather than agree to the price increase, since project scheduling and the unlikeliness of receiving lower bids at that stage made the option unfeasible. Furthermore, in addition to finding no evidence that the plaintiff had agreed to the original price amount, the Supreme Court also found written evidence from the plaintiff of its expectation to be paid the discussed adjustments in unrebutted contemporaneous correspondence. The Supreme Court therefore ruled that the rectification of the contract should be granted and amended the contract to include an additional $397,000.

As this case illustrates, negotiating parties should be careful to accurately document their negotiations by maintaining contemporaneous records while also formalizing the final terms of their deal. Failure to do so can result in protracted downstream disputes over fundamental issues, including performance terms and related pricing.

7. Never Start Work Before Finalizing the Deal
The seventh principle for negotiated RFPs is to avoid starting work under the contract until you have a signed deal. Prematurely starting work prior to finalizing the deal is a high-risk approach that results in the purchasing institution losing its leverage for negotiating the best possible terms. Selected proponents prove much more responsive if they know that they need to close the deal within the specified timeframe for negotiations or risk losing the deal to a competitor. Once contract performance is initiated, it becomes increasingly difficult for the purchasing institution to extricate itself from that supplier if the parties are unable to formalize terms. Furthermore, the time spent executing an interim “letter of intent” or “early start letter” should instead be focused on closing the final deal with speed and precision within the prescribed negotiation period. Failing to do so leaves the purchasing institution vulnerable to open-ended legal exposure.

For example, in its December 1981 decision in British Steel Corp. v. Cleveland Bridge and Engineering Co Ltd., the United Kingdom Queen’s Bench Division (Commercial Court) ordered Cleveland Bridge to pay nearly £230,000 in restitution to British Steel for the manufacture and delivery of 137 cast-steel nodes used in the construction of a bank building in Saudi Arabia, despite the absence of a written contract between the parties.

After winning a contract for the construction of a bank building, Cleveland Bridge approached British Steel to serve as a subcontractor for the supply of the required cast-steel nodes. British Steel submitted an estimated price based on incomplete information provided by Cleveland Bridge. Further negotiations ensued, which included discussions regarding the technical aspects and appropriate specifications for the manufacture of the cast-steel nodes. Cleveland Bridge then sent a letter to British Steel that stated its intention to enter into a contract, stating “We understand that you are already in possession of a complete set of our node detail drawings and we request that you proceed immediately with the work pending the preparation and issuing to you of the official form of sub-contract.” However, contrary to the contents of the letter, British Steel was not in possession of the full set of drawings and did not respond to the letter, since it expected a formal offer to follow shortly thereafter.

To prevent delays, British Steel began preparing for the manufacture of the required goods. Ongoing negotiations ensued over the specifications, with the parties agreeing that British Steel would manufacture the first cast. This cast proved to be unsatisfactory, requiring extensive alterations to the patterns and specifications. In subsequent negotiations, the parties arrived at a provisional agreement on price but continued to disagree over other contract conditions. In particular, British Steel would not agree to post a performance bond or to assume unlimited liability if the delivery schedule was not met.

In the interim, British Steel agreed to submit a revised delivery schedule and to accelerate delivery of the completed nodes. It eventually delivered all but one of the 137 nodes. Notwithstanding its prior assurances regarding progress payments, Cleveland Bridge refused to make any payment until all of the nodes were onsite in Saudi Arabia. After a stormy meeting between the parties, Cleveland Bridge continued to refuse to make payment and submitted a written claim to British Steel for damages for late delivery. British Steel countered with a claim for payment for the delivered goods.

The Court rejected the damages claim made by Cleveland Bridge for late delivery, finding that the parties never reached an agreement regarding the delivery time. Furthermore, while the Court concluded that the parties never formally entered into a contract for the nodes, it determined that British Steel was still entitled to recover a reasonable amount for the work completed based on a restitution claim.

As this case demonstrates, parties should arrive at a meeting of the minds and conclude a formal written agreement complete with all necessary specifications and performance terms prior to the commencement of any work. Furthermore, as evidenced by the restitution award to British Steel, suppliers may be entitled to compensation for their work even in instances where no contract is formed between the parties. The failure to establish a certainty of terms during contract negotiations can serve as the catalyst for future commercial disputes and subsequent legal claims.

Starting contract performance before formalizing the details of the deal is a recipe for downstream dispute. Purchasing institutions need to draw a clear line between the bidding process that leads to the formalization of a contract with the selected supplier and the actual performance of the contract, which should only begin after the deal is finalized. Negotiators need to draw a line in the sand between these two stages to avoid leaving their project teams lost in the desert of contractual uncertainty.