By Paul Emanuelli

The Canadian International continues to render contradictory rulings regarding a purchasing institution’s right to rely on bidder representations.

For example, in its August 2024 determination in Newland Canada Corporation v. The Department of Public Works and Government Services, the Tribunal found that the government improperly awarded a low-bid-wins contract to a non-compliant bidder. The dispute dealt with a solicitation for hospitality services that specified that the accommodations had to include laundry rooms. A losing bidder challenged the contract award, alleging that the contract was awarded to a competing bidder who could not meet the laundry facility specifications. While the government argued that it had the right to rely on the winning bidder’s representation that it could satisfy the contract requirements and any failure to do so was a matter of contract administration, the Tribunal disagreed.

As the Tribunal stated, the “boundary between where the procurement process ends and contract administration begins is circumstance-dependent” since “there is no bright line between the end of the procurement process and the start of the contract administration process” and “every case turns on its own facts.”

In this case the Tribunal found that the low-bid-wins evaluation rules were structured “in a manner that precluded technical evaluation of the bids” and therefore breached trade treaty evaluation rules. This case serves to further dilute the long-standing principle that government institutions have the right to rely on bidder representations regarding the ability to perform contract requirements by creating a vaguely defined duty in certain circumstances to verify a bidder’s ability to satisfy contract requirements before awarding a contract.

However, in its February 2025 determination in ADGA Group Consultants Inc. v. Department of Public Works and Government Services, the Tribunal upheld a government contract award after ruling that the tendered contract allowed for the substitution of required personnel notwithstanding the complainant’s assertion that the contract was awarded to a non-compliant bidder who had submitted a “bait and switch” bid based on personnel who were not employed by the winning bidder at the bid submission deadline.

The dispute dealt with a solicitation for the provision of technical and maintenance resources and services for electronic security systems and associated components for Correctional Service of Canada. The complainant asserted that the government awarded the contract to a non-compliant competing bidder who only hired the required personnel after the closing date of the tender call. However, the Tribunal ruled that the tendered contract allowed for the substitution of personnel and that the government had the right to rely on bidder representations that they could satisfy the contract requirements if awarded a contract. It is difficult to reconcile this ruling, where the bidder did not comply with the specification at time of bid submission but was still eligible for contract award, with the prior case where the bidder represented that it could satisfy the contract requirements after contract award, but the Tribunal found that the award was improper.

The line between evaluation decisions and contract administration decisions, which historically defined the boundary between bid protest issues and contract administration issues, continues to be blurred by recent Tribunal rulings, which serves to create further confusion regarding when purchasing institutions can rely on bidder compliance representations and when they are under a duty to investigate bidder compliance with future performance requirements. (see Tribunal Dilutes Right to Rely on Bidder Representations and Tribunal Expands Debrief Duties into Duty to Investigate for more cases on point)

The themes in this article will be explored in greater detail in the new RFx Drafting in the Canadian Public Sector certificate program that runs in May and repeats again in November. Please see our current training schedule for more details.