In its January 2015 report entitled Bluenose II Restoration Project, the Nova Scotia Auditor General found that the government mismanaged the restoration of the Bluenose II, a promotional yacht modelled after an undefeated 1920s Nova Scotia sailboat of the same name.
The Auditor General found that the restoration project, which was originally awarded to the contractor for a fixed sum of $12.5 million, ultimately cost over $19.5 million, and that the ship continued to suffer performance defects due to flawed construction.
As the Auditor General noted, the province failed to properly plan for the project, assigning project management responsibility to inexperienced staff:
The government as a whole, and the Department of Communities, Culture and Heritage specifically, did not adequately plan the Bluenose II restoration project. This started with leaving responsibility for the project with a Department having little experience managing construction projects. Construction projects like the Bluenose II restoration require a lead department with staff who are familiar with project management and construction projects in general.
The Auditor General further determined that poor planning included the failure to appropriately define roles and responsibilities for the project:
The Department did not appropriately define the roles and responsibilities for contractors or government participants in the project. While there were numerous committees involved in the project, none had terms of reference defining their roles. The impacts of not defining roles were made worse by the large number of Departments and private companies involved in the project.
The Auditor General also found that the provincial government’s rush to secure federal government funding, which only amounted to $5 million of the total project costs, led to overly optimistic scheduling, the failure to clearly define project requirements prior to construction, and the failure to set a realistic project budget:
The Department’s initial project schedule was based on meeting a deadline to comply with the Federal Infrastructure Stimulus Program. While obtaining this funding would have obvious benefits to the Province, it led to the Department setting overly optimistic end dates to comply with the requirements of the Federal program.
The Department did not prepare clearly-defined goals or requirements for the project. We also noted only one half-day risk management meeting was held. A comprehensive list of risks was not completed and little was done to prepare mitigation plans or assess the potential impact of identified risks. The meeting was held after the project manager and designer had been selected and therefore did not address risks associated with hiring for either of those key roles. Also, the Department did not ensure identified risks were adequately monitored during the project and an assessment to identify new risks was not completed.
The Department did not ensure a realistic and complete project budget was prepared, instead the preliminary cost estimate was used as a final budget. This estimate was prepared without using a robust process and as such was not an adequate first estimate, or a final project budget.
The Auditor General concluded that the lack of clear requirements contributed to project delays and resulted in cost overruns, which were exacerbated by the failure to establish late performance penalties or timely completion incentives in the contract:
When the main project contractors, project manager, designer, and builder were selected, the Department did not have sufficient details to know what would be required. This information is critical to ensure the proponents with the right skill set are selected. The lack of details was particularly evident in the construction contract, and contributed to the delays and extra costs experienced throughout the project. The Department and builder signed a fixed price construction contract before the designer prepared a detailed project specification. At that point in time, it was unclear what was to be built, resulting in weak contract terms.
The Department did not include key details concerning project expectations in the contracts signed with the project manager and the designer. The contracts did not include penalty clauses and were routinely extended throughout the life of the project. There was no monetary incentive in the contracts to complete the project in a timely manner.
Inadequate project planning resulted in a lack of clarity between the builder and the designer as to the timing and nature of drawings to be prepared. The builder indicated that they did not receive drawings sufficient to meet their needs, while the designer indicated the drawings met the requirements of the design contract.
The Auditor General also noted that the initial project deficiencies were compounded by the government’s failure to co-ordinate the various project participants and to properly address project deficiencies once they became apparent:
While planning for the project was deficient, the Department’s failure to adequately address obvious issues during the project and its failure to provide sufficient oversight, caused further problems. There were a number of stakeholders involved in the project, including the Department, builder, designer, project manager, regulatory bodies and various project committees. Ensuring these parties worked together in a professional and effective manner was critical to the success of the project. The Department had the overall responsibility to ensure these relationships were properly managed and was not able to do so. We also noted the project manager did not attend all required meetings and the Department did not always obtain required monthly status reports. Further, no comprehensive project schedule was prepared. This is a basic component of successful project management. The Department’s failure to ensure this was completed did not meet our expectation of due diligence over contract management.
As this case study illustrates, the failure to conduct proper project planning and to clearly define contract requirements at the outset of a project can set a project team on a course to inevitable failure. Once contract performance issues arise, the inherent project weaknesses that led to initial flawed project designs are likely to then manifest themselves downstream in the failure to adequately address those contract management issues. To avoid such outcomes in the future, project teams would be wise to set their course towards project success by charting a clear project management plan.