By Paul Emanuelli

This article is an excerpt from the 2020 edition of The Art of Tendering: A Global Due Diligence Guide, which is available for purchase.

In its November 2018 determination in KPMG LLP v. Department of Public Works and Government Services, the Canadian International Trade Tribunal dismissed a complaint after determining that the government maintained proper records of a re-evaluation process. The dispute dealt with a Request for Proposals (RFP) for advisory services transformation planning, implementation, management, and oversight at Employment and Social Development Canada (ESDC). The complainant, an unsuccessful proponent, challenged the re-evaluation process that led to the contract award. However, the Tribunal ruled that the Department of Public Works and Government Services (PWGSC) had the right and duty to conduct a re-evaluation of all proposals after discovering that it had initially misinterpreted the RFP during the initial evaluation. Furthermore, the Tribunal found that, notwithstanding the complainant’s assertions to the contrary, the government was not required to implement additional procedural safeguards to the re-evaluation process that went above and beyond the evaluation procedures used in the initial evaluation:

Firstly, the Tribunal is convinced that PWGSC, having determined that it may have interpreted a requirement of the RFP incorrectly, had a positive obligation to make such a correction in the evaluation (which can be referred to as a re-evaluation) of all of the bids. Had PWGSC only re-evaluated KPMG’s proposal, it would have amounted to a situation whereby bidders were not treated equally, thus violating the trade agreements.
Secondly, as far as the substance of the evaluation, the Tribunal does not find the evaluation of responses with respect to RT7 to be unreasonable, either with respect to KPMG’s bid or Deloitte’s. In this case the Tribunal is satisfied that the methodology used to arrive at the scores of the bidders was driven by a reasonable interpretation of the RFP and an equal application of the criteria to the contents both bids. Thus, the Tribunal will not interfere with the conclusions of the evaluators on this issue.
Thirdly, the Tribunal is not persuaded that any such additional procedural actions were necessary in this case. Evaluations can change before they are recorded as “final”. A correction or change made during a re-evaluation after an objection is made are similar and are also properly part of the overall evaluation process. KPMG has tried to differentiate the scenarios in terms of the process necessary to engage in one versus the other such as additional “procedural safeguards” being necessary in a re-evaluation. In effect, these arguments mean that, since the re-evaluation occurred after the initial evaluation and award, some more rigorous process and documentation may be required as a matter of course. The Tribunal’s view is that, on the contrary, it would have been problematic for PWGSC to require different methodology and documentation for the re-evaluation of the responses to RT7 than was required for its initial evaluation of this criterion.

The Tribunal also rejected the assertion that the government failed to maintain proper evaluation records during the re-evaluation. The Tribunal found that the initial evaluation results and corrected evaluation results were maintained in both individual evaluator scoresheets and in the consensus scoresheet. The Tribunal also found that there were sufficient records maintained to allow for a proper review of the record to support the bid protest:

It must be noted that the initial results and the corrected results for both KPMG and Deloitte were recorded in the individual and consensus scoresheets23 and that the initial and corrected results were communicated to KPMG, on the basis of which it formulated its initial complaint.
The records kept by PWGSC in this case, while not exhaustive, enabled KPMG to state its concerns as to these evaluations via a complaint to the Tribunal, and the Tribunal was able to adjudicate the dispute; this is what the record-keeping requirement of the trade agreements are supposed to ensure.
For these reasons, the Tribunal finds that this ground of complaint is not valid.

The Tribunal therefore upheld both the re-evaluation process and the record-keeping practices maintained during the re-evaluation and accordingly rejected the losing proponent’s complaint.