By Paul Emanuelli

While pre-bid meetings may be necessary on some projects to ensure that bidders properly understand the scope of the required work and related performance conditions, pre-bid site visits and mandatory pre-bid meetings need to be carefully managed since they create additional tendering risks that can result in bid protests and contract disputes.

Limiting the Scope of Pre-Bid Meetings
Site visits should only be required when bidders need to conduct a pre-bid physical inspection to understand material conditions relating to future contract performance. Mandatory site visit meetings should only be required where the purchasing institution controls access to the site in question which precludes prospective bidders from independently inspecting that site on their own before bidding. Otherwise, bidders should be informed that they are responsible for conducting their own pre-bid site inspections.

Site Visits to Fulfill Disclosure Duty
While public institutions can be found liable for failing to disclose material information during a tendering process, the April 2007 decision of the Ontario Superior Court of Justice in Bianchi Grading Ltd. v. University of Guelph illustrates an exception to that rule in situations where bidders are instructed to conduct site inspections prior to bidding. In this case the contractor was required to dig a 24-foot-deep trench within nine feet of an existing 12-storey building. During contract performance the contractor discovered that the building had no basement. This required the contractor to perform unanticipated shoring work to support the building before digging. The contractor sued for the additional costs of the shoring work. The Court rejected the claim, noting that the tender call made bidders responsible for inspecting the site before bidding. The Court found that the contractor should have factored the shoring costs into its original bid and refused to compensate the contractor for having “submitted its tender bid in a careless and haphazard fashion”. As the Court noted, providing compensation in this situation would undermine responsible bidding by other bidders. The Court therefore concluded that the contractor was not entitled to further payment for the shoring of the trench. As this case illustrates, bidders should take care to perform thorough site inspections prior to bidding when the tender call rules place the inspection onus on them.

Similarly, in its June 2009 decision in Clarke’s Trucking & Excavating Ltd. v. Canada (Attorney General), the Supreme Court of Newfoundland and Labrador ruled that the plaintiff contractor was not entitled to extra payments arising out of unforeseen project complications. The case dealt with a Hermitage Harbour dredging contract. The contractor, who had won the contract pursuant to a competitive bidding process, incurred $250,000 in unanticipated expenses on a contract that was originally valued at $167,000. It sued for its extra costs, alleging that the government had failed to properly disclose problematic project conditions at the site. The court rejected the claim, noting that the tender call contained provisions which put the onus on bidders to visit the site and make their own assessments of conditions before bidding. The court found that the contractor lacked experience in the particular type of dredging work and had failed to conduct a proper pre-bid site inspection. The court ultimately rejected the contractor’s claim for the unanticipated additional expenses since: (i) it found that the material encountered by the contractor fell within the specifications; and (ii) it found that the site conditions could have been discovered had the contractor conducted a proper pre-bid inspection. As this case illustrates, where the tendering provisions place an onus on bidders to conduct pre-bid inspections, this can significantly transfer the risk of additional expenses from the purchaser to the contractor. In situations where performance conditions are material to potential costs, purchasers would be wise to include site inspections in the pre-bid stage of their bidding process. For their part, bidders should ensure that they conduct diligent pre-bid site inspections since the failure to do so can have costly consequences.

Purchasing institutions should avoid pre-bid site visits or pre-bid meeting unless there is a material reason for the visit or meeting. For example, pre-bid meetings should not be used for the sole purpose of reading the solicitation document to potential bidders or for exchanging information that can be communicated in writing during the pre-bid question-and-answer addenda process.

Controlling Verbal Communications
Given the risk of future misunderstanding, pre-bid meetings should allow for inspections, but the verbal communication of information should be avoided since this can lead to subsequent factual disputes between the parties regarding the pre-bid representations made by the purchasing institution. Any follow-up questions from bidders should be managed through subsequent pre-bid communications by way of written addendum so that there is a clear record of the pre-bid communications provided to bidders.

For example, in its 2001 decision in George Robson Construction (Weston) Ltd. v. Hamilton-Wentworth (Regional Municipality), the Ontario Superior Court of Justice found that the written disclaimers in a tender call did not protect the owner from the pre-bid verbal misrepresentations made by the owner’s design consultant to the plaintiff bidder during pre-bid verbal communications. The case involved a construction project for the installation of a sewer pipe under a highway. A dispute arose over whether the contract was restricted to concrete pipe liner or also allowed for less costly steel pipe liner. The bidder claimed that the owner’s design consultant had verbally confirmed that the steel liner was acceptable and that it had calculated its price in accordance with that representation. The Court found that the bidder was prejudiced by the inaccurate verbal representation. Notwithstanding the tender call disclaimer, the Court found the owner liable due to the inaccurate verbal representation and awarded the prejudiced contractor $222,000 in damages. This case underscores the need to formalize pre-bidding communications with bidders and ensure that all such communications are reduced to written form to ensure equal access to all bidders and to reduce the risk of future misunderstandings and disagreements. While this decision was ultimately reversed by the Ontario Court of Appeal and sent for a retrial, it serves as a reminder of the importance of establishing clear communication protocols within a project team to avoid downstream disputes with contractors over project scope and specifications. (see Municipality Liable for Verbal Specification Change)

Strict Procedural Protocols
When requiring mandatory pre-bid meetings, purchasing institutions should ensure that their attendance rules are defined as strictly as their bid submission deadline rules, since the prospective bidder’s failure to attend the mandatory meeting will require a disqualification from the bidding process.

For example, in its October 2010 decision in Admiral Roofing Ltd. v. Prince George School District No. 57, the British Columbia Supreme Court upheld a School District’s decision to reject a low bidder who was late for a mandatory pre-bid site visit. The case dealt with a tender call for roofing work. The process rules included a mandatory pre-bid site visit starting at 8:00 a.m. The School District’s representatives waited until 8:05 for prospective bidders to arrive and then proceeded with the tour. The representative for Admiral Roofing arrived at 8:15 and missed part of the tour. The School District’s purchasing manager notified Admiral Roofing that it would not be eligible to bid because it missed the mandatory site visit. Notwithstanding this pre-bid notification, Admiral Roofing submitted a tender and was the low bid. After its bid was rejected, Admiral sued, arguing that it should have been allowed to bid since it had attended part of the tour and since the mandatory site visit requirement was vaguely drafted in the tender call. The Court disagreed, finding that the mandatory site visit requirement was clear and that Admiral had failed to satisfy it. Admiral also argued that the breach, if any, was minor or technical in nature and that the school district should have exercised its discretion under its privilege clause to waive the non-compliance and accept the bid. The Court disagreed. Citing prior decisions on point, it found that the breach was material and that the discretion afforded to purchasers under a privilege clause should be interpreted narrowly when dealing with tender compliance issues. As this case illustrates, purchasers should be careful to clearly draft their procedural requirements and, once established, should strictly enforce those requirements since they have limited discretion to waive them. For their part, bidders should not assume that they will be granted indulgences in instances where they fail to strictly follow the prescribed process rules.

Similarly, in its September 2015 ruling Winbridge Construction Ltd. v. Halifax Regional Water Commission, the Nova Scotia Supreme Court found that the Halifax Regional Water Commission accepted a non-compliant bid from a bidder that failed to attend a mandatory pre-bid meeting. The bid dispute involved a tendering process for a wastewater treatment facility upgrade project. After summarizing the relevant law, the Court decided that the Commission breached the tendering process rules by allowing the bidder a second opportunity to attend a site meeting without first formally amending the bidding process rules to notify other potential bidders of the rule change. This procedural irregularity was fatal to the bidding process and to the low bidder’s eligibility to submit a valid bid. (see Missed Pre-Bid Meeting Fatal to Bid Validity)

Conversely, in its January 2013 decision in Olympic Construction Ltd. v. Eastern Regional Integrated Health Authority, the Newfoundland and Labrador Supreme Court found that the plaintiff bidder’s bid was improperly rejected as non-compliant. The alleged non-compliance related to Olympic’s failure to attend an initial mandatory site meeting. However, as the Court noted, Olympic took issue with its rejection since, while missing the initial mandatory site meeting, it did attend a subsequently scheduled site meeting held by Eastern Health. The Court concluded that Eastern Health had, in effect, amended the pre-bid protocol by conducting a second site meeting. The Court found that Eastern Health had acted in bad faith by conducting a second site visit and allowing Olympic to attend that meeting and then submit a bid only to then reject Olympic’s low bid as non-compliant because Olympic had missed the initial site meeting. After finding that Eastern Health had acted in bad faith in rejecting Olympic’s low bid over the retroactive enforcement of a pre-bid procedural irregularity, the court determined that Olympic was entitled to $685,000 in lost-profit damages. As this case illustrates, inconsistencies in the enforcement of procedural norms can give rise to significant liability. Purchasing entities may be prevented from reverting to a strict enforcement of their process rules in situations where they expressly or implicitly waive strict adherence to those rules during their tendering process. (see Newfoundland Health Tenders Trigger Bid Shopping and Bid Compliance Claims)

Further, purchasing institutions should ensure that their mandatory pre-bid meetings are easily accessible for all prospective bidders to avoid late attendance. For example, in its September 2012 decision in Traveler Elevator v. Florida School for the Deaf and the Blind, the Florida Division of Administrative Hearings upheld the Florida School for the Deaf and the Blind’s decision to cancel the tendering process and re-tender the contract due to irregularities at a mandatory pre-bid meeting. The case dealt with an Invitation to Bid for an elevator repair and maintenance contract. As the Court noted, the solicitation included the requirement of a mandatory pre-bid meeting. One of the bidding teams, Otis, arrived late for that meeting after a computer failure at the building security desk delayed the issuance of visitor security badges but they were still allowed to attend the meeting and later submitted the winning bid. A competing bidder brought a bid protest to challenge that award. Due to the bid protest and the concerns over the validity of the mandatory pre-bid meeting, the School decided to cancel the contract award and re-tender the project. While the complainant challenged the cancellation decision, arguing that it should have been awarded the contract, the Court ultimately agreed that the process should be cancelled and re-tendered due to confusion caused by the procedural irregularity at the mandatory pre-bid meeting. As this case illustrates, procedural irregularities should be avoided whenever possible since they subject a tendering process to potential subsequent legal challenges. (Security Desk Delays Undermine Pre-Bid Meeting)

Establishing Protocols and Avoiding Improvisation
In addition to establishing and following strict protocols for mandatory pre-bid meetings, purchasing institutions should also ensure that they can administer the site visits or pre-bid meetings without creating barriers to access since timely attendance needs to be strictly enforced. Where pre-bid site visits or meetings are necessary, project scheduling should provide for sufficient advanced notice for potential bidders to make travel arrangements to attend those meetings. Further, when mandatory pre-bid meetings are required, purchasing institutions should formally establish more than one meeting time so that potential bidders who are late or cannot attend the first meeting have an opportunity to attend a later meeting. Purchasing institutions should avoid improvising these processes since, as illustrated by the above-noted cases, midstream rule changes can result in future compliance disputes.

The themes in this article will be explored in greater detail in our new Fundamentals of Canadian Government Procurement certificate program that runs in April and returns in October. Please see our current training schedule for more details.