In its April 2019 report entitled Space Acquisitions: DOD Faces Significant Challenges as it Seeks to Address Threats and Accelerate Space Programs, the U.S. Government Accountability Office (GAO) found that optimism bias was causing significant program delays and cost overruns in the acquisition of U.S. Department of Defense (DOD) space systems.
By way of background, the GAO noted that “DOD space systems provide critical capabilities that support military and other government operations” and that they are “expensive to acquire and field, costing billions of dollars each year.” The GOA report focused on DOD efforts to update its satellite systems and raised concerns over whether those funds were being effectively used. As the GAO report stated, “DOD is simultaneously undertaking new major acquisitions to replenish its missile warning, protected communications, navigation, and weather satellites”, while at the same time “boosting efforts to increase space situational awareness and protect space assets”. The GAO noted that these “widespread acquisition activities could face a wide range of resource and management challenges.”
The report raised concerns over the technical complexity, institutional challenges, and personnel challenges faced by the program. With respect to technical complexities, the GAO noted that the increased threats to satellites posed by hostile adversaries, which included jamming and cyberattacks, as well as increased threats posed by space debris, required DOD to make “changes to how it designs its space systems to increase the resilience and survivability of space capabilities”. With respect to institutional challenges, the report noted that “DOD is planning major changes to leadership for space” that included recently proposed legislation to establish a United States Space Force to “consolidate existing military space activities and minimize duplicative efforts across DOD”. However, the GAO noted that “open questions remain about governance as new programs get underway and whether the changes themselves may result in further fragmentation.” Finally, with respect to personnel challenges, the GAO noted that “DOD has begun over 9 new space programs at a time when it is also seeking increased investments in ships, aircraft, and the nuclear triad, among other programs” and that “it is unclear whether DOD has a sufficient workforce to manage its new programs.”
The GAO report also stressed that the DOD should manage its space system acquisitions carefully to “avoid repeating past problems” which included a series of prior satellite launches that produced suboptimal results:
Our prior work has shown that many major DOD space programs have experienced significant cost increases and schedule delays. For instance, the total program cost for the Advanced Extremely High Frequency (AEHF) satellite program, a protected satellite communications system, has grown 117 percent since the program’s original cost estimate and its first satellite was launched more than 3.5 years late. For the Space Based Infrared System (SBIRS), a missile warning satellite program, the program cost grew 265 percent from its original estimate and the launch of the first satellite was delayed roughly 9 years. Both programs moved to the production phase where fewer problems tend to surface, and where there is typically less risk of significant cost and schedule growth. A more recent major satellite program, Global Positioning System (GPS) III, has seen an almost 4-year delay due to technical issues and program cost growth of about 32 percent.
Cost and schedule growth has also been a challenge for satellite ground systems and user equipment. Ground system delays have been so lengthy, that satellites sometimes spend years in orbit before key capabilities can be fully exploited.
The GAO concluded that overly optimistic planning that underestimates the risk and complexity of major projects is a significant contributing factor to ongoing cost overruns and project delays:
Cost and schedule growth in DOD’s space programs is sometimes driven by the inherent risks associated with developing complex space technology; however, over the past 10 years we have identified a number of other management and oversight problems that have worsened the situation. These include making overly optimistic cost and schedule estimates, pushing programs forward without sufficient knowledge about technology and design, and experiencing problems in overseeing and managing contractors, among others. We have also noted that some of DOD’s programs with operational satellites, such as SBIRS, were also exceedingly ambitious, which in turn increased technology, design, and engineering risks. While SBIRS and other satellite programs provide users with important and useful capabilities, their cost growth has significantly limited the department’s buying power at a time when more resources may be needed to protect space systems and recapitalize the space portfolio.
As this report illustrates, even the most technologically sophisticated organizations face significant challenges in successfully executing their major projects. Public institutions would be well-served to ensure that they implement the proper project governance practices and properly resource and staff those projects to better ensure successful execution.