By: Paul Emanuelli

This article is an excerpt from The Art of Tendering: A Global Due Diligence Guide, which is available for purchase.

In its March 2020 report entitled Evaluation of Niger Air Base 201 Military Construction, the Inspector General of the U.S. Department of Defense (DoD) found that the military failed to properly execute on the construction of a $50 million airfield and base camp in Niger. As the report determined, the U.S. Africa Command (USAFRICOM) failed to properly plan and execute the project and significantly underestimated the required construction costs, which resulted in contract-splitting, the failure to obtain proper approvals, and suboptimal technical results in the final construction of the airfield:

We determined that USAFRICOM and the Air Force did not effectively plan, design, and construct Air Base 201 in Niger to provide airfield and base support infrastructure in support of USAFRICOM operations. Specifically, we identified the following problems.
  • The Air Force built runway shoulders without congressional authorization when it submitted a DD Form 1391 to Congress that excluded runway shoulders in the project scope. Furthermore, AFAFRICA significantly underestimated the project cost, which created risk that the Air Force would not complete the MILCON project. As a result, and reducing the thickness of pavement in certain areas of the airfield.
  • The Air Force bypassed congressional notification when it split the construction requirement for ISR operations into six O&M projects totaling $5.4 million, with each O&M project cost ranging from $399,000 to $1.8 million. Because each portion of the project was under $2 million, the Air Force was permitted to use O&M appropriation. AFAFRICA representatives stated that they programmed the six O&M projects to meet USAFRICOM’s urgent operational timeline. However, all of the projects were known and each project on its own would not result in a “complete and useable facility,” which means the projects should have been combined and reported to Congress.

As the Inspector General detailed, the project team failed to scope and cost the project in accordance with applicable standards, and improperly subdivided the initiative into six separate sub-projects, which resulted in the failure to obtain required approvals or meet safety and security requirements:

Problems Existed in the Planning, Design, and Construction of Air Base 201
USAFRICOM and the Air Force did not effectively plan, design, and construct Air Base 201 in Niger to provide airfield and base support infrastructure in support of USAFRICOM operations. Specifically, AFAFRICA did not plan the MILCON scope and cost in accordance with applicable standards. For example, the Air Force excluded runway shoulders from the MILCON scope and underestimated MILCON costs for facilities such as relocatable aircraft shelters and base perimeter fence. Also, AFAFRICA programmed six separate O&M projects even though there is existing guidance on combining the projects. The Air Force also constructed guard tower foundations that did not meet required specification, in terms of size, for the permanent guard towers that AFAFRICA acquired. In addition, AFAFRICA acquired the permanent guard towers without congressional notification. Furthermore, USAFRICOM and AFAFRICA did not perform thorough site surveys to design the airfield and plan for sources of construction materials and equipment. AFCEC/CFED, 823rd RED HORSE, and 31st ERHS also did not design and construct Air Base 201 infrastructure in accordance with applicable DoD standards to meet safety and security requirements, including the aircraft rescue and firefighting station, base perimeter fence, and airfield lighting.

The Inspector General also found that the project underestimated costs by nearly $12 million and exceeded its scope of approvals when it added paved shoulders to the runway, which exceeded the approved budget:

Air Force Did Not Accurately Capture Scope and Cost of Facilities on Approved DD Form 1391
The Air Force built runway shoulders without congressional authorization when it submitted a DD Form 1391 to Congress that excluded runway shoulders in the project scope. Specifically, AFAFRICA excluded 28,800 square meters of runway shoulders from the DD Form 1391 scope and cost estimate. Furthermore, AFAFRICA significantly underestimated the project costs, for elements such as the relocatable aircraft shelter and base perimeter fence, by at least $11.9 million, which created risk that the Air Force would not have sufficient funding to complete the MILCON project. To address these underfunded aspects of the project, the Air Force took cost saving measures such as reducing the thickness of the pavement in certain aircraft parking areas.
Runway Shoulders Were Added to the Scope of the Project Without Authorization
The Air Force built runway shoulders that it excluded from the DD Form 1391; therefore, the runway shoulders were built without congressional authorization. The constructed runway measured approximately 95,000 square meters, including the runway shoulders. However, the congressionally-approved DD Form 1391 listed a line item for 68,240 square meters of runway, which excluded approximately 28,800 square meters of shoulder. According to 10 U.S.C. § 2853 (2016), the MILCON scope of work, in terms of function, size, and quantity, may not be increased above the amount specified in the DD Form 1391 provided to Congress. The MILCON Program Manager stated that the 31st ERHS built the runway shoulders as part of the MILCON because shoulders were essential to the runway, even though they were excluded from the DD Form 1391.

Furthermore, the Inspector General found that guard towers were added to the project without proper authorization, and that guard tower foundations were improperly built and rendered potentially unusable:

The Air Force Acquired Permanent Guard Towers Without Congressional Notification and Constructed Guard Tower Foundations That Were Potentially Unusable
The Air Force potentially violated the Antideficiency Act when it acquired 12 permanent guard towers costing approximately $3.7 million using a Procurement funds instead of MILCON funds that would have required Air Force approval and congressional notification. In addition, the Air Force constructed foundations meant for temporary guard towers that could potentially be unusable because the permanent guard towers required larger foundations.
The Air Force Acquired Permanent Guard Towers Without Congressional Notification
The AFAFRICA A4C, A4S, and A4P bypassed the Air Force approval and congressional notification process when it programmed the funding for the permanent guard towers costing approximately $3.7 million with Procurement funds instead of MILCON funds. An AFAFRICA A4C representative stated that AFAFRICA considered the guard towers “equipment,” at a cost of approximately $300,000 each, which qualified for Procurement funding. The representative further stated that the AFAFRICA A4C considered the guard towers equipment and not construction because the towers were relocatable, as specified in DoD Instruction (DoDI) 4165.56. DoDI 4165.56 defines relocatable buildings as prefabricated structures that are designed and constructed to be readily moved, erected, disassembled, stored, and reused. In addition, the DoDI 4165.56 identifies the use of relocatable buildings as temporary or interim in nature. DoDI 4165.56 also requires the use of MILCON funding, not Procurement funding, for relocatable buildings if classified as real property and total acquisition and construction costs exceed $2 million under 10 U.S.C. § 2805 (2017).
The Air Force Constructed Guard Tower Foundations That Were Potentially Unusable
The Air Force constructed eight foundations for temporary guard towers that were potentially unusable because the 12 permanent guard towers that the Air Force purchased required larger foundations. According to the MILCON Program Manager, he was not aware that AFAFRICA planned the acquisition of the 12 permanent guard towers and that larger foundations were required. The MILCON Program Manager stated that he and the 31st ERHS understood that the AFAFRICA A4C planned the purchase of eight temporary guard towers, as identified in the congressionally-approved DD Form 1391. Because of this, AFCEC/CFED planned and executed contract services through the Logistics Civil Augmentation Program to complete the construction of eight guard tower foundations for temporary guard towers in March 2016. The MILCON Program Manager stated that he was not aware that larger foundations were necessary during the time the guard tower foundations were being constructed from April 2016 to February 2017.

The Inspector General also determined that the site surveys were inadequate to prevent construction planning problems, noting that the project team did not conduct appropriate soil sampling and topographic analyses, which resulted in pavement compaction and drainage problems, and created the need for further design modifications:

Site Surveys Were Not Sufficient to Prevent Airfield Design and Construction Planning Problems
USAFRICOM and the Air Force did not perform complete site surveys to gather information needed for design and construction. Specifically, the Air Force did not conduct complete soil sampling and topographic analysis, which created airfield pavement compaction and drainage problems. The Air Force also experienced logistical problems such as material and equipment shortages during construction because the site survey did not identify sources of construction materials.
UFC 3-260-02 states that the design of airfield pavement must be based on complete and thorough site surveys, including soil sampling, topographic analysis, and identification of material sources. However, a site survey conducted in July 2014 consisted of limited soil samplings and a limited topographic survey. The AFAFRICA site survey team, led by the AFAFRICA pavement engineer, also did not identify possible sources of materials in the area. At remote locations where engineering data are not readily available, site surveys can take 2 to 3 weeks to gather comprehensive engineering data; however, the Air Base 201 site survey occurred within 12 hours because of security concerns in Niger.
In October 2015, USAFRICOM and the Air Force conducted another pre‑construction site survey, which focused on additional soil sampling. Similar to the July 2014 site survey, security concerns limited the October 2015 site survey to 7 hours and prevented the team from collecting necessary testing and topographic data.
Limited Soil Sampling Resulted in Design Modifications
The AFAFRICA site survey team conducted limited soil sampling that did not provide sufficient information on the predominant soil type at the airfield. According to UFC 3-260-02, representative soil samples should be obtained and classified to detect problematic soil types that could compromise pavement compaction and strength. As a result of the limited soil sampling, the AFAFRICA site survey team misclassified the soil as cohesive type, instead of a cohesion-less soil type that requires moisture and compaction at a greater depth. Because of the misclassification, the Air Force had to increase the designed pavement depth by 39 inches after the start of the project, which required additional materials and construction time. Also, the limited soil samples prevented effective planning for construction equipment. For example, the 31st ERHS did not have the proper equipment for soil compaction and had to resort to using loaded trucks instead of pad foot rollers.
Limited Topographic Survey Resulted in Grading and Drainage Problems
In addition, the site survey team conducted limited topographic analysis to identify slopes, flat terrain, and the floodplain in the area of the planned airfield. Because of the limited topographic analysis, the team did not get adequate information to properly design grading and drainage. This problem became apparent when the June 2016 rainy season revealed large amounts of water accumulation in the east area of the runway, which resulted in the drainage design being adjusted. In addition, during the construction of the life support area, but before the construction of the airfield, the 31st ERHS and the 823rd RED HORSE determined that the original airfield location needed to be shifted 200 feet because the topographic and geotechnical characteristic at the original location was not suitable for the airfield. However, the shift in the airfield location exacerbated the soil identification problem, as previously discussed, because the soil samples collected at the original location were not representative of the area for which the airfield was to be constructed.

The Inspector General also found that the project team failed to properly identify the sources for the required construction materials and overestimated the availability of construction materials in the region:

Sources of Materials Not Identified During the Site Survey Resulted in Material Shortage
The site survey team did not identify sufficient sources of materials as specified in UFC 3-260-02, which states that areas within the airfield site or a reasonable haul distance from the site should be explored for possible sources of materials. The Air Force overestimated the availability of construction materials in the region. Specifically, the 31st ERHS had to search the region for a local vendor to supply an estimated 292,000 metric tons of base material.34 The 31st ERHS identified a local vendor, but that vendor had the capability to produce only 8,000 metric tons of base material per month; the amount needed would have taken approximately 3 years to produce. The 31st ERHS eventually located another local vendor with the capability to produce 30,000 metric tons of base materials per month, which greatly improved the construction schedule.

The Inspector General also concluded that the project team failed to effectively oversee and co-ordinate the planning, design, and construction of the base, which resulted in unapproved cost overruns and poor record-keeping:

USAFRICOM and the Air Force Lacked Oversight and Coordination in the Planning, Design, and Construction of Air Base 201
The planning, design, and construction problems at Air Base 201 occurred because USAFRICOM and the Air Force did not effectively oversee and coordinate the planning, design, and construction of Air Base 201. Specifically, we did not find any evidence to demonstrate that AFAFRICA leadership reviewed, validated, and approved the MILCON planning and programming of Base 201. According to AFI 32-1021, the major command validates each MILCON project and confirms by a signed letter that the DD Form 1391 data are accurate and complete. However, an AFAFRICA A4C representative stated that there was no signed letter from AFAFRICA leadership validating the accuracy and completeness of the DD Form 1391. Furthermore, AFAFRICA leadership did not ensure that responsible individuals maintained records to support actions throughout the planning process of Air Base 201. For example, there were no decision memorandums to show that AFAFRICA leadership and USAFRICOM were engaged in and oversaw the decisions to limit the site surveys because of security concerns in Niger.
The Air Force also conducted limited oversight of AFAFRICA planning and programming processes. Specifically, AFI 32-1021 identified the required process for MILCON planning and programming initiated at the installation level, which is then validated at the major command level—such as AFAFRICA—and then submitted to Air Force Headquarters for approval. However, AFI 32-1021 did not identify oversight responsibilities when the major command initiates MILCON planning and programming. Accordingly, Air Base 201 planning and programming may not have received the level of review and scrutiny intended by AFI 32-1021.

The Inspector General found that these project execution failures ultimately resulted in significant adverse operational outcomes given the three-year delay in completion and the ongoing safety and security concerns created by the suboptimal final construction:

Air Base 201 Infrastructure Was Delayed in Supporting USAFRICOM Operations by 3 Years
As a result, the Air Force was delayed in supporting the USAFRICOM ISR mission by almost 3 years from the planned construction completion date of October 2016 identified on the DD Form 1391. In addition, the problems that we identified relating to the aircraft rescue and firefighting facility, and airfield lights could lead to increased risk in safety and security. Furthermore, the construction of the infrastructure necessary to support ISR missions, such as munitions storage and handling areas, has not been completed. To accept the risk associated with the lack of infrastructure, the Air Force approved temporary waivers in June 2019 to allow ISR operations at Air Base 201. However, operating without the infrastructure to support increases the safety risk for personnel operating at Air Base 201.

As a result of these findings, the Inspector General recommended that the Air Force update its policies “to identify oversight responsibilities when troop labor construction projects are planned and programmed at the major command level” and “establish a coordination and decision-making process with key stakeholders for troop labor construction projects”. The report also recommended that the Air Force retroactively submit the required congressional notification of scope changes for the expanded runway, and that it “initiate a preliminary review to determine whether the use of Procurement funds for the acquisition of the guard towers resulted in a potential Antideficiency Act violation and, if so, conduct a formal investigation and provide the results of the review to the DoD Office of Inspector General.” As this case study illustrates, weak project planning and co-ordination, coupled with the failure to realistically assess cost and complexity, inevitably results in suboptimal project execution and the failure to achieve operational objectives on time and on budget. That weak planning also increases the risk of breaching applicable procurement oversight rules and regulations. This serves as a useful reminder to all project teams of the importance of good governance in successful project execution.