In its December 2024 report entitled Administration of Contracts for Interpretation Services, the Office of the Procurement Ombud concluded that the federal government’s attempt to use a contract extension process to impose contract amendments that increased performance requirements while decreasing payments to interpretation service providers was unreasonable.
After the proposed amendments resulted in 37 contractor complaints being filed with the Office of the Procurement Ombud, that office investigated the issue and released its investigation report. As the Ombud’s report detailed, the proposed amendments would have required interpretation contractors to time-track the time that elapsed during the “suspension” of in-progress parliamentary committee meetings and exclude that time from their billable hours. While the original contract defined non-billable time to include waiting time prior to the start of meeting when those meetings were delayed due to “technical or obstruction reasons,” the original contract did not exclude the time during which in-progress meeting were “suspended” from the billable hours of the interpretation contractors. The proposed amendment would introduce what one complainant referred to as “stop-watch interpreting,” requiring interpreters to track the time during unscheduled meeting suspensions so that interpreters would no longer be paid for the time they were on stand-by waiting for meetings to resume.
As one complainant stated, “I am absolutely not prepared to show up to work with a stopwatch in hand for a job that, in principle, is billed by the day, not by the hour and even less by the minute.” That contractor found it “particularly shocking” that the amendment proposed to “stop the clock for each suspension during the meeting,” noting that a meeting that is “interrupted by numerous suspensions is often more stormy, more aggressive, and therefore more stressful for the interpreters” who are required to stay on stand-by waiting for the meeting to resume.
As that complaint further detailed, when a parliamentary committee meeting chair “suspends the meeting, he does not announce a ‘15-minute break’ during which we are free to go get a coffee, he announces a suspension for an indefinite period.” Those ad-hoc suspensions are “often used to negotiate a new text of an amendment to a motion, for example” after which the meeting may resume with little notice.
The Ombud agreed that this proposed change, where interpreters would no longer be paid for the time that they were on stand-by during meeting suspensions, constituted a substantive amendment to the original terms of the contract that “changed the way in which Complainants invoice for hours worked, and introduced a new timekeeping methodology.” The Ombud concluded that the government’s proposed amendment “would have increased the Suppliers’ administrative burden while reducing potential payment available for the increased level of effort.”
After concluding that the proposed contract change constituted a substantive amendment, the Ombud then considered whether the government had acted reasonably in attempting to impose the amendment during a contract extension process. On that issue, one complainant asserted that the government had tried to “obfuscate by sending emails falsely claiming that we had misunderstood, and that the amendment was not a substantive change at all.” That complainant characterized the attempted amendment process as “one of intimidation, coercion and obfuscation.” A second complainant asserted that the government “tried to intimidate the interpreters by giving an arbitrary and a very tight deadline” for accepting the changes and that the government also “tried to gaslight us by sending emails falsely claiming that WE had misunderstood everything and that nothing was in fact changed.”
The Ombud concluded that the government’s attempt to impose these substantive contract changes under artificial time-pressures, while implying that the changes were a condition of extending the original contracts, was unreasonable.
More specifically, the Ombud noted that the federal government’s Directive on the Management of Procurement refers to “collaboration, fairness, openness, and transparency” and requires federal government departments to “manage contracts in a way that is both fair to and collaborative with suppliers.” The Ombud concluded that the government’s attempt “to initiate substantive changes to the contract on a very short timeline undermined the Suppliers’ ability to properly consider those changes” and that this decision was contrary to “the principles of fairness and collaboration” established under the above-noted Directive.
This report, which illustrates why public institutions should adopt and adhere to formal contract management protocols that mandate the fair and reasonable treatment of contractors, will be featured in the Managing Supplier Performance and Debarment module of our new Fundamentals of Canadian Government Procurement certificate program that runs in April and returns in October. Please see our current training schedule for more details.