Recent bid protests put a spotlight on evaluation disputes that could have been avoided with more precise document drafting and more disciplined evaluation procedures. These new disputes reveal chronic issues that have persisted for decades as public institutions continue to struggle with their basic bidding procedures.
For example, in its November 2024 decision in Canada v. EllisDon Corporation, Canada’s Federal Court of Appeal upheld the award of financial compensation to a bidder who was improperly awarded a contract due to an evaluation error and then had that award revoked. A prior Canadian International Trade Tribunal ruling found that the government improperly rejected a low bid after mishandling an electronic bid bond and then delayed rectifying that error for a protracted period before revoking the original award. (see Federal Government Liable for Mishandled Bid Bond).
This recent error is not an isolated incident. Rather, it reflects decades-long evaluation issues that have persisted in recent federal bid disputes. For example, in 2023, bid process errors resulted in three separate bid protests. In the first dispute, a contract award had to be cancelled and retendered due to the government’s failure to respond to a pre-bid question. (see Missed Pre-Bid Question Fatal to Federal Award) In the second dispute the Tribunal criticized the government’s failure to properly notify a bidder of its bid protest rights during a debriefing. (see Tribunal Urges Government to Notify Bidders of Protest Rights). In the third dispute, the government was sued after it mismanaged a pre-bid addenda process, made multiple evaluation errors, and then mismanaged the post-award debriefing process. (see Addenda and Debrief Miscommunications Triggers Protest)
In that same year unclear mandatory requirements resulted in three other federal bid disputes. The first dispute involved the cancellation of a bidding process due to a vague mandatory requirement that resulted in no compliant bids. (see “Malleable” Federal Mandatory Leads to RFP Failure) The second dispute resulted in a re-evaluation order due to a “latent defect” in a mandatory requirement. (see “Latently Ambiguous” Mandatory Triggers Re-Evaluation). The third dispute resulted in a lost profit damages award after the government failed to clearly state how it would evaluate mandatory pricing information. (See Failure to Evaluate Extension Pricing Fatal to Fair Award)
Then in 2024 the federal government faced another three bid disputes over evaluation procedures. In the first dispute the government was challenged for using a tie-breaker process that was not included in its original solicitation. While the government successfully defended the process by drawing on an obscure evaluation procedure in the trade treaty rules, a clear tie-breaker rule in its original solicitation could have avoided the legal dispute and prevented the contract award delays. (see Tribunal Upholds BAFO Tie-Breaker Process) The second case involved a compliance dispute where a bid had to be rejected since the bidding rules did not permit bidders to rectify pricing errors, even though the government had adopted rectification procedures in prior years in other procurements. (see Feds Restrict Price Rectifications). In a third dispute, the Tribunal awarded lost profit damages against the government due to a flawed re-evaluation that was ordered after the government conducted a flawed initial evaluation on that same project. (see Feds Double Down on Evaluation Error).
These drafting and evaluation errors are not limited to federal government procurement. For example, in its March 2023 decision in 837386 Yukon Inc v. Yukon, the Supreme Court of Yukon ruled that the administration of the First Nations Procurement Policy resulted in unfairness to the rejected applicant since the eligibility criteria were not transparent. As this case illustrates, adopting evaluation preferences does not give institutions free license to make non-transparent evaluation decisions. (see Yukon Challenged on First Nations Procurement Policy)
Similarly, in its June 2025 decision in HP Consultants Inc. v. IIDI, the Supreme Court of Prince Edward Island rejected a losing bidder’s allegations of a hidden “rural presence” criterion after finding that the factor could be reasonably interpreted as falling within the broader “regional development” requirement stated in the RFP. However, more precise drafting, with express reference to a “rural presence” in the evaluation criteria, could have avoided the interpretive dispute from ever going to court in the first place. (see PEI Court Rejects Hidden Criteria and Interference Claim)
Further, in its November 2025 decision in Bot Construction et al. v. Minister of Transportation, the Ontario Superior Court of Justice upheld an arbitration decision that awarded a contractor $14 million in extra contract costs after concluding that the costs of handling “excess rock” on a highway expansion project were not included in the scope of the original $55 million contract award. Since the risk of excess rock was foreseeable during the tender call drafting stage, a more precise treatment of this issue in the original project specifications could have avoided the extra cost dispute. (see Ontario Ministry Rocked with $14M Extras Award)
These persistent drafting and evaluation issues illustrate why public institutions need to refocus on the fundamentals of clear document drafting and consistent evaluation procedures if they hope to avoid similar future bid protests and contract disputes.
The themes in this article will be explored in greater detail in our new RFx Drafting in the Canadian Public Sector certificate program that runs in May and returns in November. Please see our current training schedule for more details.