By: Paul Emanuelli

This article is an excerpt from The Art of Tendering: A Global Due Diligence Guide.

In its March 2020 report entitled Defence capabilities – delivering what was promised, the UK Comptroller and Auditor General attributed ongoing delays in major military procurements to the lack of training and resourcing of project teams. In particular, the report stressed that project staff needed better training to avoid optimism bias when setting project timelines.

The Auditor General found that the Department of Defence faced “major risks to the timely delivery of nearly one-third of its most significant capabilities” and that these delays could “affect the Department’s ability to meet external threats to national security, leave gaps in capability and require use of existing capabilities beyond their normal lifetime at increased cost.” The report attributed these delays to a lack of skill, training, and resources on project teams, and to an over-reliance on external consultants:

Commands and delivery teams lack capacity and skills, which affects delivery of the capability. Under-resourced project and delivery teams contribute to delays in delivery. Six of the 32 DMPP capabilities face shortfalls of more than 20% in their programme teams. Our 2019 report Reforming the civilian workforce drew attention to the issue of a lack of suitably qualified and experienced personnel in the Department. There are particular shortages of engineering and commercial staff, and some teams are very reliant on consultancy support.

The Auditor General stressed the need to train project teams on “the importance of recognising and avoiding optimism bias in reporting of progress.” The report also noted the importance of proper time management on major projects, stating that project teams should be allowed “enough time to carry out their roles when appointing them and look at how they can balance competing demands.” In fact, the Auditor General found that from both a project-delivery and technical-competence perspective, the overall lack of capacity and capability significantly contributed to the systemic project delays:

Availability of skilled personnel
Deliverability can also be undermined by a lack of capacity and capability in the departmental teams responsible for delivery. Under-resourced teams in the Commands acting as the customer, as well as in the delivery organisations, contribute to delays in delivery. Skills and capabilities are a serious concern for nine of the 32 DMPP capabilities. Our 2019 report Reforming the civilian workforce drew attention to the shortages of suitably qualified and experienced personnel in the Department. There are particular shortages of engineering and commercial staff, and some delivery teams are very reliant on consultancy support. Concerns about this challenge are most common in Strategic Command. Six of the 32 DMPP capabilities face shortfalls of more than 20% in their programme teams. Three have a delivery confidence assessment of amber, and three have an assessment of amber/red or worse. Digital and nuclear programme teams display a particular reliance on external consultants to provide expert input to programme teams.

As this report illustrates, the failure to ensure that project teams are properly trained and adequately resourced results in systemic project delays and corresponding delays in meeting the operational needs that depend on the timely execution of procurement processes. Public institutions that want to avoid similar systemic delays should prioritize the proper training and staffing of their procurement teams.